Planning for the 2020-2029 P5.0 STIP completed.
- December 4, 2018: All Projects are submitted and in review by NCDOT.
- Draft STIP for public review and comment: January 2019.
- October 11, 2018: Final Division Needs Points
- July 18th, 2018: Final Regional Impact Points Assignment
- May 8, 2018: Citizens Invited to Participate in the Transportation Planning Process
- May 8, 2018: Draft Regional Impact and Division Needs Project Scores
Project Documents
NWPRPO Methodology Comments & Responses
NWPRPO Public Participation Plan
Timeline
| Phase I: Identification of Projects | |
| County & Municipal Pre-submittal Meetings | Spring 2017 |
| Public Call for Projects | July – Aug 2017 |
| TAC approval of project submittal list | June 2017 |
| Projects entered into SPOT Online | July – Sept 2017 |
| Phase II: Scoring and Ranking of Projects | |
| TAC considers draft ranking and scoring process | December 2017 |
| Scores and draft list of programmed statewide mobility projects released | March 2018 |
| Deadline for approval of local input point assignment methodologies | March 21, 2018 |
| County TIP Meetings and Public Outreach Meeting | March - April, 2018 |
| NWPRPO submits Regional Impact project list to NC DOT | April – June 2018 |
| Draft list of programmed regional impact projects released | July – August 2018 |
| NWPRPO submits Division Needs project list to NC DOT | October 2018 |
| Final P5.0 scores released | Nov – Dec 2018 |
| 2020-2029 Draft STIP released | January 2019 |